Sunderland Project

For this project, we collaborated with Brock and Sons Construction, who handled the initial excavation for a heated parking area between the garages. Our team took over to form the driveway, preparing it for Styrofoam insulation and heat lines. To ensure durability, we reinforced the entire area with rebar before completing the pour and stamp in a single day. The following day, we returned to clean, seal, and cut the surface for a polished, lasting finish.

The larger pour was also a heated driveway, where we managed to pour 100 cubic meters and stamp it all in a single day to prevent color variations or joints. This attention to detail allowed for a seamless, uniform look. After 24 hours, we came back to wash, cut, and seal, with the driveway ready for use within a week.

As an all-in-house company, we offer excavation and landscaping services, streamlining the process without waiting on external teams. With a crew of 15 skilled professionals, we handle large-scale projects with efficiency and expertise.